The Hatters Way and Chaul End Lane roundabout rebuild runs 16 weeks from 29 June. Live works, M1 junction 10 closures, car park prices and the busway.
One scheme is disrupting Luton traffic more than any other this summer: the rebuild of the Hatters Way and Chaul End Lane roundabout, which Luton Borough Council started on Monday 29 June 2026 and expects to run for 16 weeks, taking it into mid-October.
A second decision is due within days. The council’s recommendations for Bury Park, including an 18-month trial red route, went to its Overview and Scrutiny Board on 27 July and the Executive is due to make the final call this month.
What is happening now
| Where | What | When | Source |
|---|---|---|---|
| Hatters Way and Chaul End Lane roundabout | Junction rebuild: dedicated left turn, signal-controlled crossings, new shared foot and cycleway | 16 weeks from 29 June 2026 | Luton Council |
| Bury Park | Red route trial, footway parking restrictions, loading bay changes | Executive decision August 2026 | Luton Council |
| M1 junction 10 northbound | Overnight exit slip road closures, 22:00 to 05:00 | Wednesday 12 and Thursday 13 August 2026 | National Highways |
Hatters Way and Chaul End Lane
The junction is being rebuilt rather than resurfaced, so the disruption lasts. The council’s scheme adds a dedicated left turn from Hatters Way into Chaul End Lane, signal-controlled crossings on Hatters Way and Dallow Road, a new shared pedestrian and cycle footway on the western arm of the roundabout, and a modified bus lay-by on Dallow Road. Overnight closures between 8pm and 5am, Monday to Friday, were used in the first week. The council’s own line is blunt: “There will inevitably be some disruption while these improvements are carried out.”
Bury Park
The council published its recommendations on 16 July 2026 after technical work and a public consultation held in autumn 2025. The headline proposals are an 18-month trial red route with a three-minute grace period, removing parked cars from around formal crossing points, footway parking restrictions, and 120 parking spaces at Luton Town Football Club made available except on matchdays. Loading bay hours would extend from 7pm to 7am out to 7pm to 10am, with the maximum stay rising from 30 to 45 minutes, and disabled bay stays would go from 60 to 90 minutes. A one-way system on Kenilworth Road is no longer recommended. If the Executive approves it, the council has proposed reviews after six and twelve months.
The M1 at junction 10
Junction 10 is the main motorway access for Luton and the airport, and it is where most of the overnight motorway work in this area lands. National Highways’ closure report for the week of 7 to 13 August 2026 listed the northbound junction 10 exit slip road closed from 22:00 to 05:00 on Wednesday 12 and Thursday 13 August, as part of a wider scheme covering the northbound carriageway between junctions 8 and 10. Nothing was listed at junction 11.
Junction 10 is also a long-term problem the council has already named. Its draft Local Transport Plan 5 lists “increasing capacity at M1 Junction 10 with National Highways to support airport expansion” as a longer-term priority, alongside Vauxhall Way corridor improvements and an access road for the airport business park. With airport passenger numbers set to roughly double to 32 million a year, that junction is going to keep appearing in the news. What that expansion means for the town is covered in Luton planning news.
How to check what is shut today
Nothing on this page replaces a live check before you set off. The three sources that actually carry current Luton closures are:
- one.network for council and utility roadworks street by street. This is where Luton Borough Council points residents.
- National Highways for the M1, including its weekly seven-day closure report, which is the only place overnight slip road closures are published in advance.
- Luton Borough Council news for the schemes big enough to warrant an announcement, which is where both the Hatters Way and Bury Park items above came from.
Parking in Luton
Council car park prices are lower than most towns on this line, and the overnight rate is the detail worth knowing.
| Stay | Cost |
|---|---|
| 1 hour, Monday to Friday | £1.30 |
| 3 hours, Monday to Friday | £2.60 |
| All day, Monday to Friday | £7.20 |
| All day Saturday | £3.00 |
| All day Sunday and bank holidays | £2.00 |
| Overnight, 6pm to 8am, any day | £2.00 |
A weekly permit for Crawley Road is £25, a month is £85 and a year is £1,000, with fixed-day annual permits from £477 for two days a week. Payment across the council’s car parks is by PayByPhone or by telephone on 01582 851 141; you need the location ID, which is 802301 for Crawley Road.
Chapel Viaduct car park 1 in the town centre is the trap. It is a private car park Monday to Friday and only opens to the public at weekends and on bank holidays, when Saturday parking runs from £1.50 for an hour to £5.20 for five hours and Sunday is £2 all day. Turning up on a Tuesday will not work.
The council also runs small car parks, most of them open 24 hours, at Beech Hill, Birch Link, Bramingham Road, Brunswick Street, Hitchin Road, Mostyn Road and Round Green.
Parking at the stations
If you are driving to the train rather than into town, the three station car parks hold 824 spaces at Luton Airport Parkway, 753 at Luton and 376 at Leagrave. Fares and journey times from each are in Luton train times to London.
Buses and the guided busway
Luton’s most distinctive piece of transport infrastructure is the Luton to Dunstable guided busway. The council counts six miles of dedicated busway inside the borough, with nine bus routes providing 18 buses an hour along it. Because it is segregated from traffic, it is the one corridor in the town that roadworks like the Hatters Way scheme do not slow down, which makes it the sensible fallback while that junction is being rebuilt.
The council’s draft Local Transport Plan proposes going further, with feasibility studies on extending the busway to Leighton Buzzard and other centres, and a target of a bus every five minutes along the core route.
For the airport, the Luton DART runs from Luton Airport Parkway station to the terminal in four minutes, 24 hours a day, at £4.90 for an adult single.
Frequently asked questions
What roadworks are happening in Luton right now?
The Hatters Way and Chaul End Lane roundabout is being rebuilt, a 16-week scheme that began on 29 June 2026 and runs to about mid-October. For street-level detail on smaller works, check one.network, which is where the council directs residents.
When will the Hatters Way roadworks finish?
The council said the works would take 16 weeks from Monday 29 June 2026, which puts completion in mid-October 2026.
What is the Bury Park red route?
A proposed 18-month trial that would restrict stopping on the main Bury Park roads, with a three-minute grace period, alongside footway parking restrictions and 120 parking spaces at Luton Town FC on non-matchdays. It was recommended on 16 July 2026 and the council’s Executive is due to decide in August 2026.
How much is parking in Luton town centre?
At the council’s Crawley Road car park, £1.30 for an hour, £7.20 all day Monday to Friday, £3 all day on Saturday and £2 on Sunday. Overnight between 6pm and 8am is £2 any day.
Is the M1 closed at junction 10?
Not in the daytime. National Highways listed overnight closures of the northbound junction 10 exit slip road, 22:00 to 05:00, on 12 and 13 August 2026. Check the seven-day closure report for the current week before travelling late.
Sources
- Work set to start on improvement works at major Luton junction, Luton Borough Council, 26 June 2026, for the Hatters Way and Chaul End Lane scheme, its start date, duration and contents.
- Bury Park traffic improvement recommendations published, Luton Borough Council, 16 July 2026, for the red route trial and the decision timetable.
- National Highways seven-day road closure report for M1 junction 10 overnight slip road closures in the week of 7 to 13 August 2026.
- Luton Council draft Local Transport Plan 5, 2026 to 2040 for busway mileage and frequency, M1 junction 10 capacity plans and corridor priorities.
- Crawley Road car park and Chapel Viaduct car park 1 for tariffs, spaces and payment methods.
- Luton DART tickets and fares for DART price, journey time and hours.
Roadworks change constantly. Everything here was checked on 13 August 2026; confirm against one.network and National Highways before you travel.